On 4 May 2026, news reports said MahaRERA had sent show cause notices to 8,212 of the state’s 33,029 ongoing housing projects for missing the 20 April QPR deadline. Most were in the Mumbai Metropolitan Region and Konkan (4,644), followed by the Pune region (2,311). Promoters were given 60 days to respond and upload the pending reports.

That window has closed, and we have not seen published figures on how it ended. But the deadline repeats every quarter, so the next round of notices is worth preparing for. If one reaches you or your client, here is what it means and a sensible order of work.

What the notice rests on

As reported by Punekar News, the May notices treated a missed QPR as a violation under section 7 of the Real Estate (Regulation and Development) Act, 2016, and cited sections 3, 4, 5 and 11 together with Order No. 33/2022, which sets out what must be updated and when.

Section 7 matters because it is the revocation section. It lets the Authority revoke a registration where a promoter defaults on what the Act, rules or regulations require. It also gives the promoter two protections:

  • Section 7(2): a registration cannot be revoked unless the Authority has given at least 30 days’ written notice stating the grounds, and has considered any cause the promoter shows in that time.
  • Section 7(3): instead of revoking, the Authority may let the registration continue on further terms set in the allottees’ interest.

So a notice is a real chance to fix the default and explain it. It is also the formal first step towards losing the registration.

What it can lead to

The consequences reported for the May 2026 notices were:

  • cancelling the registration or keeping it in abeyance,
  • freezing the project’s bank accounts,
  • banning advertising, marketing and sale of flats,
  • telling registration authorities not to register sales in the project, and
  • a penalty, reported as ₹50,000.

MahaRERA’s chairman said in the Free Press Journal’s report that a registration would be cancelled or kept in abeyance if a developer still did not update its QPR after repeated follow-ups.

These are not empty warnings. Realty Quarter’s account of a 2023 round describes the escalation: a 15-day warning, then a 45-day notice, then 363 registrations suspended. Of those, 72 promoters corrected their records and paid a fine. The remaining 291 were given a final date before revocation.

A practical order of work

MahaRERA has not published a standard reply format that we could find, so follow whatever your notice asks for. This is the order we would work in.

1. Read the notice for four things

Note the date it was issued, the project registration number, the quarters it names, and the response period. Count your deadline from the notice itself, not from a news report or from a colleague’s notice.

2. List everything outstanding, not only what the notice names

Open the project on the portal and compare it with what Order 33/2022 requires. A notice about one quarter may sit on top of an older missed quarter, or an overdue Form 5 or Form 2A. It is better to clear all of it in one pass than to answer one notice and receive another.

3. Work out what each missing quarter needs

For each quarter, the order asks for changes in building plan approvals, physical progress, and the booking status of units and garages.

A quiet quarter still needs an update. If nothing was withdrawn from the designated account that quarter, the order asks for a self-certification of the amount deposited. A stalled site does not remove the obligation.

4. Get the certificates, oldest quarter first

If withdrawals were made, each one needs Forms 1, 2 and 3. Ask for missing certificates in one list, per professional, rather than one quarter at a time. Working from the oldest quarter also means each quarter’s closing figures can feed the next.

Be careful with figures reconstructed months later. An architect or CA can only certify what they can support, so keep the bank statements and ledgers behind each figure. Our Form 3 worked example shows which numbers have to agree.

5. File, then reply

Upload the pending reports and save each acknowledgement. Then reply within the period, stating what was outstanding, what has been filed and when, and attaching the acknowledgements. If there is a reason for the delay that you want considered, state it plainly with evidence.

6. Take advice in the harder cases

Bring in a RERA advocate or your advisor if you dispute the notice, cannot finish in time, have a project whose registration has lapsed, or already have a suspended registration. A lapsed project usually has a second problem to solve, which we cover in when do MahaRERA QPRs stop?

Make sure there isn’t a next notice

Most missed QPRs aren’t decisions. They are a project nobody was watching, a professional nobody chased, or a promoter who assumed the consultant had filed. Three habits cover most of that:

  • One list of every project, including stalled and nearly finished ones, with its next due date and who is responsible.
  • Requests that go out at the start of the quarter’s window, as in our QPR fortnight plan.
  • The acknowledgement saved with the quarter, so you can show what was filed and when, without searching.

ReraQPR is built around that list. It shows every project’s due date and missing documents, sends reminders to professionals on its own, and keeps the acknowledgement with the quarter. Start a free trial: three months free with one project, no credit card required.


Sources: Punekar News, 4 May 2026; Free Press Journal, 4 May 2026; Realty Quarter, 10 October 2023; MahaRERA Order No. 33/2022, as reproduced by TaxGuru; section 7 of the Real Estate (Regulation and Development) Act, 2016, as quoted in Swapnil Promoters v. Union of India.

This article is general information about MahaRERA requirements as we understand them on the date above, not legal or professional advice. Orders and circulars change; check the MahaRERA website or your advisor before relying on it.