When do MahaRERA QPRs stop? Occupancy certificates, Form 4 and lapsed projects
“The building is finished. Do we still file?” Every consultant gets asked this, and the honest answer takes a little longer than yes or no.
Order No. 33/2022, the order that sets out regular updates, doesn’t state when quarterly updates end. Consultants’ guides differ on whether an occupancy certificate is enough or whether all closing obligations must also be met. So the cautious position is the one to work from: keep filing until the project’s completion documents are on the portal and it no longer shows as ongoing. If a project is in a grey area, ask MahaRERA’s helpdesk and keep the reply.
Here is what we can say with more confidence.
What completion requires
The order lists two completion updates: Form 4 with the OC number, and the occupancy certificates issued for the project.
Form 4 is the architect’s certificate on completion of the registered project. The form lists each occupancy or completion certificate by number, building or wing, date and planning authority. The architect certifies that the project is complete in all aspects as per the agreement for sale, and the promoter countersigns.
That table shows why partial completion is the common trap. An OC for wing A says nothing about wing B. If the registered project includes both, it isn’t complete when the first certificate arrives.
Form 4 without an OC doesn’t count
MahaRERA’s possession stage page describes Form 4 as issued by the architect after the OC is received. Uploading Form 4 first doesn’t close the project.
In the Kuber Ganraj matter, reported in January 2026, a promoter had uploaded a Form 4 dated 2 December 2020 but never obtained an OC. MahaRERA reportedly held that this wasn’t legal completion, because the architect’s certificate only attests to construction, and possession without an OC isn’t permitted.
The exception is plotted development where local rules provide no OC or completion certificate. Order No. 37/2022 says a duly filled Form 4 signed by the architect denotes completion there, and ties completion to the Tahsildar’s acknowledgement of the intimation of non-agricultural use.
What continues after the OC
An OC doesn’t end the paperwork:
- Conveyance disclosure. Order 33/2022 asks for a disclosure signed by the promoter and the association of allottees, confirming conveyance, three months after the OC.
- Form 5 and Form 2A. The order sets no exception for them on completion, so check with your CA before dropping the last year’s annual filings.
- Society or association formation, if it hasn’t happened yet.
When the completion date passes without an OC
This is the most common way a project gets into trouble. The registration runs to the date the promoter declared. Without an OC or an extension by then, the project appears on MahaRERA’s lapsed list.
A lapsed registration doesn’t end the project’s obligations. In 2023, MahaRERA pursued projects already in abeyance over missing QPRs, and a show cause notice can follow. A lapse also doesn’t take away buyers’ claims.
The routes back, according to MahaRERA’s FAQ:
| Route | What it gives |
|---|---|
| Extension under section 6 | A period decided by the Authority, up to one year in aggregate |
| Extension under section 7(3) | Decided case by case, where more time is needed |
| Removal from the lapsed list | Follows Order No. 24/2021 and MahaRERA’s review of the documents uploaded |
If a project stays lapsed or its registration is revoked, section 8 comes into play. The FAQ says the association of allottees has the first right of refusal to carry out the remaining work.
Check the 2026 automatic extension first
On 7 August 2026, MahaRERA extended registrations by four months, citing force majeure linked to the West Asia conflict. As reported, it covers projects whose completion date falls on or after 28 February 2026, needs no application, and excludes projects registered on or after 1 August 2026.
So recalculate completion dates before you assume a project has lapsed, or that it has as long as you thought. The report doesn’t say whether other obligations change, and nothing suggests QPRs pause during the extra months. Read the order itself before relying on it.
A quick way to sort your list
This table is our reading of the above, as a working rule. It isn’t a statement from MahaRERA.
| The project today | QPRs | Do next |
|---|---|---|
| Under construction, within its date | Keep filing | Watch the completion date |
| Date within six months, no OC in sight | Keep filing | Prepare the extension early |
| OC for some wings only | Keep filing | Collect the rest, then Form 4 |
| Form 4 uploaded, no OC | Keep filing | Get the OC; Form 4 alone doesn’t close it |
| Lapsed | Bring up to date | Apply for extension; take advice |
| OC for everything, Form 4 uploaded | Confirm on the portal | Conveyance disclosure; last annual filings |
| Abandoned or never started | Keep filing until told otherwise | Deregistration needs a MahaRERA order; take advice |
Nearly finished projects are the ones most likely to fall off a tracker, and they are the ones with least to gain from a late filing. ReraQPR keeps every active project on the register each quarter until someone marks it completed or archives it, so one can’t drop off because a person assumed it was done. Start a free trial: three months free with one project, no credit card required.
Sources: MahaRERA Order No. 33/2022 and Order No. 37/2022, as reproduced by TaxGuru; MahaRERA Form 4; MahaRERA FAQ; Square Feat India, January 2026; Free Press Journal, 7 August 2026.
This article is general information about MahaRERA requirements as we understand them on the date above, not legal or professional advice. Orders and circulars change; check the MahaRERA website or your advisor before relying on it.