The 20th of each quarter gets all the attention, but it is only one of several obligations. MahaRERA Order No. 33/2022, dated 5 July 2022, sets out what a promoter must keep up to date on a registered project, and it replaced Order No. 18/2021. It groups the updates by timing. Put together, they look like this.

The whole list

WhenWhatWho supplies it
Within 20 days of each quarter endQPR: plan approval changes, physical progress, booking status of units and garagesPromoter, consultant
Each quarter with no withdrawalSelf-certification of the amount deposited in the designated accountPromoter
Each withdrawalForms 1, 2 and 3 to the bank, with copies on the portalArchitect, engineer, CA
Within 3 months of financial year endForm 2A, the quality assurance certificateEngineer
Within 6 months of financial year endForm 5, the annual statement of accountsCA
When they changeEncumbrance and CERSAI reports, project professionals, litigation detailsPromoter
Within 3 months of a majority of allottees bookingFormation of the legal entity, such as a societyPromoter
On completionForm 4 with the OC number, and the occupancy certificatesArchitect, promoter
3 months after the OCConveyance disclosure signed by the promoter and associationPromoter, association

The next fixed dates

These are the dates from now until October 2027. Our due dates page keeps the QPR dates current.

DateDue
20 January 2027QPR for October to December 2026
20 April 2027QPR for January to March 2027
30 June 2027Form 2A for 2026–27
20 July 2027QPR for April to June 2027
30 September 2027Form 5 for 2026–27
20 October 2027QPR for July to September 2027

Note how the annual items land: Form 2A and Form 5 each fall twenty days before the next QPR. You will be chasing the same engineer and CA for that QPR’s certificates, so ask for both together.

The ones that get missed

Form 2A

Form 2A is the easiest to forget, because it has no link to withdrawals and nothing else depends on it. It comes from the engineer, once a year. Put 30 June on the calendar now.

Form 5

Form 5 comes from the CA who is the annual auditor of the promoter’s company or firm, which may not be the CA who signs your Form 3s. Its deposits table works out:

  1. the total collected from allottees,
  2. the amount that should have been deposited,
  3. the amount actually deposited in the designated account, and
  4. the shortfall or excess.

It does this for the year and for the project to date, leaving out pass-through charges and indirect taxes. So a quarter’s unexplained shortfall will reappear in Form 5 with a CA’s signature under it. That is a good reason to clear these as you go, using the checks before Form 3.

The self-certification

If there was no withdrawal in a quarter, the QPR still needs a statement of what was deposited. People tend to assume that no withdrawal means nothing to do. The order says otherwise.

Event-driven updates

A new CA, a new loan and fresh encumbrance, a new court case: these have no due date of their own, which is why nobody files them. The simple fix is to make them a question you ask every quarter. “Has anything changed: professionals, encumbrances, litigation, plan approvals?” Then record the answer, even when it is no.

Conveyance

Three months after the OC, the project has usually dropped out of everyone’s attention. The disclosure needs the association’s signature as well, so it takes longer to collect than it looks. Our note on when QPRs stop covers what else continues after the OC.

Consequences

Order 33/2022 itself is about what to update, and it doesn’t list penalties. But MahaRERA’s May 2026 show cause notices cited the order, among other provisions, for missed disclosures. Separately, MahaRERA’s FAQ notes that failing to comply with an order of the Authority can draw a daily penalty under section 63, which may cumulatively reach 5% of the project’s estimated cost.

Keeping it all in one place

A spreadsheet with one row per project and one column per obligation works for a while. It stops working when a date slips without anyone being told.

ReraQPR puts these items on each project’s quarterly checklist: Forms 1, 2 and 3, Forms 2A and 5 in the right quarter, bank statements and ledgers, bookings, plan approvals, changes in professionals, encumbrances and conveyance status. Each professional gets an upload link and a reminder when something is late. Start a free trial: three months free with one project, no credit card required.


Sources: MahaRERA Order No. 33/2022, as reproduced by TaxGuru; MahaRERA New Forms page; MahaRERA FAQ.

This article is general information about MahaRERA requirements as we understand them on the date above, not legal or professional advice. Orders and circulars change; check the MahaRERA website or your advisor before relying on it.

See your next quarter in ReraQPR before the 20th.

Free for 3 months with one project. No credit card required.