How much can be withdrawn? The Form 3 limit, worked through with numbers
Form 3 is often described as “the CA’s certificate”. For the promoter, its most important line is near the bottom of Table B: the net amount that can be withdrawn from the designated account under this certificate.
Here is how that figure is reached, using the format on MahaRERA’s website, which was published in the Maharashtra Government Gazette in December 2021. The project below is made up, and the amounts are in ₹ crore.
Table A: what the project is estimated to cost
| Estimated cost | ₹ crore |
|---|---|
| Land cost: land value, premiums, TDR, stamp duty and similar | 30 |
| Construction, as certified by the engineer | 49 |
| Additional items not in the estimate, as per the engineer | 1 |
| Other development cost: salaries, consultants, site overheads, services | 12 |
| Taxes, cess, fees and premiums to statutory authorities | 5 |
| Interest on construction borrowing | 3 |
| Total estimated cost | 100 |
The form’s notes exclude pass-through charges and indirect taxes, and say the estimate is revised through a correction application.
Table B: what has been incurred
Table B follows the same headings, with one rule that matters more than any other. For construction, the form takes the lower of the cost certified by the engineer and the actual cost in the books as verified by the CA.
Suppose the engineer certifies ₹22 crore and the books show ₹24 crore. The form uses 22.
| Cost incurred to date | ₹ crore |
|---|---|
| Land cost | 30 |
| Construction: lower of engineer (22) and books (24) | 22 |
| Additional items, as per the engineer | 1 |
| Other development cost | 5 |
| Taxes, cess, fees and premiums | 2 |
| Interest on construction borrowing | 1 |
| Total cost incurred | 61 |
From cost to the withdrawal limit
| Line | ₹ crore |
|---|---|
| Proportion of cost incurred to total estimated cost (61 ÷ 100) | 61% |
| Amount which can be withdrawn (100 × 61%) | 61 |
| Less: amount withdrawn to date | 52 |
| Net amount which can be withdrawn under this certificate | 9 |
The current format lists these lines without printing the multiplication. The calculation of total estimated cost multiplied by the proportion comes from the earlier version of the form, as taught in ICAI’s guidance to CAs. Check it with your CA against the current format.
Three things the example shows
The limit is really the cost incurred
Multiply it out and the total estimated cost cancels: 100 × (61 ÷ 100) is simply 61. So the cumulative limit equals the eligible cost incurred to date, and revising the estimate changes the percentage rather than the limit. Almost any argument about Form 3 is really an argument about what counts as cost incurred, and how much of it can be supported.
Lagging books reduce the limit
Now suppose the books are behind and show ₹20 crore of construction, while the engineer still certifies ₹22 crore. The lower figure is now 20:
| Books at 24 | Books at 20 | |
|---|---|---|
| Construction taken | 22 | 20 |
| Total cost incurred | 61 | 59 |
| Net withdrawable | 9 | 7 |
Bills not yet entered in the books have cost this promoter ₹2 crore of limit this quarter. Updating the books before the CA starts is the cheapest fix available.
The percentage isn’t physical progress
Form 1 states physical progress, building by building. Form 3’s proportion is a cost measure. In this example, land alone accounts for 30% before a single slab is cast, so the two percentages can differ widely and legitimately. Don’t enter one where the other is asked for, and be ready to explain the gap if someone asks.
The limit isn’t the cash
The certificate sets a ceiling, and it doesn’t put money in the account. If the separate account holds ₹6 crore, the promoter can take out ₹6 crore at most, even though the certificate allows ₹9 crore.
It also comes with procedure. Under Order No. 33/2022, Forms 1, 2 and 3 go to the bank for a withdrawal, with copies uploaded to the MahaRERA portal at the same time. If nothing was withdrawn in a quarter, the QPR takes a self-certification of the amount deposited instead.
Table D: when 70% becomes 100%
Form 3 also carries a test that is easy to overlook, marked “to be filled for ongoing projects only”. It compares what is still to be spent with what can still come in:
| Table D | ₹ crore |
|---|---|
| Balance cost to complete (100 − 61) | 39 |
| Balance receivable from sold units | 15 |
| Unsold area valued at the ready reckoner rate | 20 |
| Estimated receivables | 35 |
If estimated receivables exceed the balance cost, 70% of balance receivables goes to the designated account. If they are lower, as here, the form says 100% of balance receivables goes there. A project in this position that keeps sweeping 70% would deposit less than the form asks for.
What to check before the CA signs
- Amount withdrawn to date agrees with the separate account’s statements from the first withdrawal, not just this quarter’s.
- Construction in the books and the engineer’s Form 2 are as of the same date, and the gap between them is understood.
- Form 2’s estimated cost matches Table A, and any revision has been through a correction application.
- Pass-through charges and indirect taxes are out of the cost figures.
- Table C’s balance receivables agree with the bookings in the QPR.
The same deposit and withdrawal figures come back in the annual Form 5, which reports any shortfall in the designated account for the year and for the project to date.
ReraQPR helps with the parts that go wrong most often. Reconciliation compares withdrawals with cost incurred and flags a 70% shortfall, and when a signed Form 3 comes back, AI reads its figures and compares them with your approved QPR figures. You still review and confirm every suggestion. Start a free trial: three months free with one project, no credit card required.
Sources: MahaRERA Form 3, New Forms page; MahaRERA Order No. 33/2022, as reproduced by TaxGuru; Guidance to CAs, Nagpur Branch of WIRC of ICAI. The project and its figures are invented to illustrate the arithmetic.
This article is general information about MahaRERA requirements as we understand them on the date above, not legal or professional advice. Orders and circulars change; check the MahaRERA website or your advisor before relying on it.