Reconciling Tally books with RERA bank accounts before a QPR, step by step
A CA who receives reconciled figures with every difference explained usually signs Form 3 quickly. One who receives raw ledgers sends back a list of questions, and the quarter slips. Here is how to do the reconciliation first, for one project. It works the same way for twenty.
Step 1: Get the books, by project
Ask the promoter’s accountant for an export covering the period, and ask for the same format every quarter. In Tally, open the Day Book or a voucher register from Display, set the period, and export it to XML or Excel.
The important question is how the books separate projects. If one company runs several projects, entries need to carry the project, usually through a cost centre or separate ledgers. If they don’t, sort that out with the accountant first, because everything after this depends on it.
Then sort the ledgers into the categories Form 3 cares about: collections from allottees, land cost, construction cost, other development cost, statutory payments and interest.
Step 2: Get all three bank statements
You need the collection, separate and transaction accounts, as required since July 2024, each covering the whole quarter. Older projects may have a different account structure, so note what each project actually has.
Before using a statement, check that the opening balance plus movements equals the closing balance. Also check that it starts where last quarter’s ended. A missing page is much easier to catch here than later. Statements often end on the last transaction rather than the month end, so a gap of a few days at the end isn’t necessarily a problem, but do confirm it.
Step 3: Match collections to the collection account
Match each receipt in the books to a deposit in the bank, allowing a few days for clearing. Whatever doesn’t match goes on a list.
Here is an invented quarter, in ₹ lakh:
| ₹ lakh | |
|---|---|
| Collections in the books | 240.00 |
| Less: cheque booked 30 September, cleared 2 October | (5.00) |
| Add: bank transfer received 29 September, not yet in the books | 1.50 |
| Expected deposits in the collection account | 236.50 |
| Actual deposits per statement | 236.50 |
| Difference | 0.00 |
The books and bank disagree by ₹3.5 lakh, yet both are right. The first item is a timing difference that clears itself next quarter. The second means the books need an entry. Keep the two kinds apart, because only the second needs someone to act on it.
Watch for GST. Form 3 and Form 5 leave pass-through charges and indirect taxes out of collection figures. If the books post receipts gross in one ledger and net in another, you will see a difference that isn’t real. Agree one treatment with the CA and apply it every quarter.
Step 4: Check the 70%
Compare what reached the separate account with 70% of collections. Do it cumulatively as well as for the quarter, since Form 5 reports both the year and the project to date.
| ₹ lakh | |
|---|---|
| Deposits in the collection account this quarter | 236.50 |
| 70% of that | 165.55 |
| Transfers received in the separate account | 160.55 |
| Shortfall | 5.00 |
A shortfall isn’t always a breach. The transfer may have happened on the first day of the next quarter, for example. But it needs a reason on record before the QPR is filed. If the project’s Form 3 Table D says 100% rather than 70%, test against that instead.
Step 5: Tie withdrawals to cost
Take every debit from the separate account and find what it paid for in the books. Then check three things:
- Each withdrawal maps to land cost, construction cost or another permitted use.
- Cumulative withdrawals don’t exceed the limit on the latest Form 3.
- Nothing in the account belongs to another project. Mis-postings are common when one promoter uses the same bank for several projects.
Step 6: Record every difference
For each open item, record the amount, the date, the reason and who confirmed it. Most differences fall into a few types:
| Type | Example | What happens next |
|---|---|---|
| Timing | Cheque clears after quarter end | Should clear next quarter; check that it did |
| Not yet booked | Bank charge, interest, unentered receipt | Accountant books it |
| Wrong posting | Receipt in another project’s ledger | Accountant corrects it |
| Bank error | Duplicate debit | Promoter raises it with the bank |
| Genuine shortfall | 70% transfer not made | Promoter transfers; CA is told |
Start next quarter by re-checking last quarter’s open items. An old timing difference that hasn’t cleared wasn’t a timing difference.
Step 7: Compare with what you filed
Last, compare this quarter’s figures with last quarter’s filing and with the signed certificates. Cumulative collections and cost shouldn’t fall without a reason, and last quarter’s closing figure should be this quarter’s opening. If they don’t agree, find out why before the CA asks.
Then send the CA the figures and the explanations together, with Forms 1 and 2 attached.
Doing this for twenty projects
The steps are simple. The difficulty is doing them twenty times in the days before the 20th, with statements in different formats.
ReraQPR imports Tally XML, Excel or CSV books and bank statements, including PDFs, which AI reads and checks against running balances. You map ledgers and cost centres to projects once. It then runs these checks and sends every unmatched item to a review queue until someone records why it differs. AI can suggest the likely reason, and you confirm it. Start a free trial: three months free with one project, no credit card required.
The figures in this article are invented to illustrate the method. Form 3 and Form 5 references are to the formats on MahaRERA’s New Forms page.
This article is general information about MahaRERA requirements as we understand them on the date above, not legal or professional advice. Orders and circulars change; check the MahaRERA website or your advisor before relying on it.